• Provincial Road Improvement Project (ADB Assisted)

LOAN 3756-PAK: KHYBER PAKHTUNKHWA

PROVINCIAL ROADS IMPROVEMENT PROJECT

 

Progress of Dualization of Mardan-Swabi Road 42.05 KM

 

Brief of the Project

Total Length 42.05 KM
Date of Commencement 16 October 2019
Date of Completion 15 April 2022
PC-I Cost PKR 9,400.1 Million
Contract Cost PKR 6,711.138 Million
Revised Contract Cost (utilities) PKR 7,287.873 Million
Achieved Physical Progress 58.43%
Planned Physical Progress 97.17%
Lag -38.73%
Achieved Financial Progress 57.95%

 

Bar Chart of Progress

Over All

OVERALL PROJECT

58.43%
97.18%

LOT -1

LOT 1(RD 0+000 TO RD 22+00)

57.60%
97.18%

LOT -2

LOT 1(RD 22+000 TO RD 42+00)

59.27%
97.18%
Achieved
Planned

 

Project Progress of Lot-I

Achieved Progress 57.60%
Planned Progress 97.18%
Lead/Lag -39.58%

Physical Progress

Trench Excavation 17.77/22.00
Filter Layer Widening 17.58/22.00
Improved Subgrade 17.58/22.00
Sub Base Trench 17.43/22.00
Aggregate Trench 14.98/22.00
Aggregate C.Way (Top Layer) 14.10/22.00
Asphaltic Base Course 10.69/22.00

Bridges

Piles 158/158
Pile Caps 21/21
Transoms 21/21
Casting of Girder 100/104
Launching of Girder 64/104
Deck Slab 06/14
Culvert R/S 39/47
Culvert L/S 40/47

Project Progress of Lot-2

Achieved Progress 59.27%
Planned Progress 97.18%
Lead/Lag -37.91%

Physical Progress

Trench Excavation 18.21/20.00
Filter Layer Widening 17.60/20.00
Improved Subgrade 17.60/20.00
Sub Base Trench 17.40/20.00
Aggregate Trench 16.98/20.00
Aggregate C.Way (Top Layer) 15.14/20.00
Asphaltic Base Course 12.58/20.00

Bridges

Piles 60/60
Pile Caps 09/09
Transoms 09/09
Casting of Girder 35/38
Launching of Girder 16/38
Deck Slab 01/06
Culvert R/S 33/33
Culvert L/S 32/33

 

View All Projects

 

 

 

 

View All Projects