• Provincial Road Improvement Project (ADB Assisted)

S.no Road Name Length(KM) Progress/Status  
1 SHAH ALAM TO SARDARYAB ROAD 11.95 KM 82.59% Completed View Details
2 UMERZAI TO HARICHAND ROAD 29.02 KM Substantially Completed View Details
3 RISALPURE TO JEHANGIRA ROAD 36.68 KM Substantially Completed View Details
4 KHAIR ABAD TO NIZAM PUR ROAD 23.10 KM Substantially Completed View Details
5 ADINA TO YAR HUSSAIN ROAD 24.73 KM Substantially Completed View Details
6 SANGI MARMAR ROAD (Eastern ByPass) 17.00 KM Substantially Completed View Details
7 SANGI MARMAR ROAD (Western ByPass) 16.40 KM Substantially Completed View Details
8 MAQSOODA TO KOHALA ROAD 33.38 KM 92.62% Completed View Details
9 HARIPUR HATTAR TAXILA ROAD 21.97 KM 95.63% Completed View Details
Total 214.80 KM

 

Brief of the Project

Length 214.80 Km
Date of Commencement July-2018
Date of Completion (Ongoing works) March 2022
Original PC-I Cost PKR 17,103.0 Million
Contract Cost ( ongoing) PKR 15,428.33 Million
Expenditure up to Date PKR 14,151.42 Million
Achieved Physical Progress 96.79 %
Planned Physical Progress 98.08%
Lag -01.29 %
TOC Issued 178.368 Km
Asphaltic Base Course 209.172 Km
Asphaltic Wearing Course 208.122 Km

 

Dualization of Mardan-Swabi Road

S.no Road Name Length(KM) Progress/Status  
1 Dualization of Mardan-Swabi Road 42.05 KM 58.43% View Details
Total 42.05 KM

 

Additional Road

S.no Road Name Length(KM) Progress/Status  
1 KALAM-MATILTAN-MAHODAND ROAD 34.70 KM Last date for submission of Bidding documents is 10 May, 2022 View Details
Total 34.70 KM