LOAN 3601-PAK: KHYBER PAKHTUNKHWA
PROVINCIAL ROADS IMPROVEMENT PROJECT
Progress of Haripur- Hattar-Taxila Road 21.97 KM
Achieved Progress | 95.63% |
Planned Progress | 100.0% |
TOC | 15.514 KM |
Balance Work | |
Earthwork | 441 Meters |
Sub Base | 441 Meters |
Aggregate Base Course | 441 Meters |
Asphaltic Base Course | 500 Meters |
Asphaltic Wearing Course | 500 Meters |
Shoulder/Drain | 441 Meters |
Ancillary Work | All Items |