LOAN 3601-PAK: KHYBER PAKHTUNKHWA
PROVINCIAL ROADS IMPROVEMENT PROJECT
Progress of Maqsood-Kohala- Pir Sohawa Road 33.38 KM
Achieved Progress | 92.62% |
Planned Progress | 100.0% |
TOC | 28.468 KM |
Balance Work | |
Subgrade Preparation | 590 Meters |
Sub Base | 590 Meters |
Aggregate Base Course | 710 Meters |
Subgrade Preparation | 590 Meters |
Asphaltic Base Course | 710 Meters |
Asphaltic Wearing Course | 900 Meters |
Shoulder PCC (Linear Meter) | 5000 Meters |
Drain | 750 Meters |
Launching of Girders (25+600) | 20 Np (Arrangements in Progress) |
Deck Slab (25+600) | 05 Slabs |
Approach Slab & NJB (11+300,25+600) | 04 Nos |
Ancillary Work | All Items (Partially Done) |