LOAN 3601-PAK: KHYBER PAKHTUNKHWA
PROVINCIAL ROADS IMPROVEMENT PROJECT
Progress of Shah Alam Sardaryab Road 11.95 KM
Achieved Progress | 82.59% |
Planned Progress | 96.33% |
TOC | 10.755 KM |